Local Highway Maintenance Transparency Report 2025 - 2026
Section 1 - Introduction to our highway network
The Department for Transport requires all local highways authorities to publish information about their highways maintenance activities to help local taxpayers see the difference that funding is making in their areas.
1 Our highway network
Gateshead Council, as the highway authority, has a legal responsibility to maintain adopted highway in the borough (except the A1 and A194(M), which are maintained by National Highways). Most adopted highway has been in existence for many years, but the network continues to change as a result of new development or alterations to existing routes to accommodate modern requirements.
The total length of the highway network in Gateshead is approximately 560 miles (900km). The network reflects the mixed character of Gateshead, ranging from major urban routes carrying large volumes of traffic to more lightly used rural roads some over 200 metres in altitude providing access to outlying villages and farms. It includes 740 miles (1191km) of footway, 32,000 streetlights, 289 bridges and other highway structures, and 170 traffic signaled junctions or crossings.
Gateshead's position within the Tyneside conurbation means that, as well as catering for local traffic, there are significant amounts of travel through the area to and from adjoining areas. The Newcastle / Gateshead urban core (including Newcastle city centre) is the main regional centre for shopping, leisure and employment providing over 80,000 jobs, and draws on a wide regional catchment area. This results in additional pressures on the main cross boundary routes from commuter and other traffic. These are intensified by the limited number of river crossings, which means that traffic converges at a small number of points on the network. The council shares maintenance responsibilities with Newcastle City for a number of bridges across the Tyne.
Table 1.1 Lengths of highways, footways and cycleways
Type of highway | Length in kilometres (km) |
---|---|
A road | 78.1 |
B and C road | 141.4 |
Unclassified roads | 682.2 |
Total roads | 901.7 |
Footways | 1191 |
Other public rights of way | 254 |
Cycleways | 178.2 |
Section 2 - Highways maintenance spending
Table 2 Annual financial allocations
Financial year | Capital allocated by DfT (£) | Total capital investment Council and DfT (£) | Revenue spend (£) | % spent on preventative Maintenance (Capital) | % spent on reactive maintenance (Revenue) |
---|---|---|---|---|---|
2025/26 * | 5,413,000* | 8,586,000* | 4,577,612* | 65* | 35* |
2024/25 | 4,797,129 | 8 688,248 | 4,400,990 | 66 | 34 |
2023/24 | 4,331,957 | 7,734,705 | 4,609,261 | 63 | 37 |
2022/23 | 4,490,617 | 6,870,886 | 3,802,290 | 64 | 36 |
2021/22 | 4,012,720 | 7,961,814 | 3,871,502 | 67 | 33 |
2020/21 | 6,107,913 | 8,519,750 | 3,053,774 | 74 | 26 |
* Estimate
2.1 Reactive (revenue) budget types of activity
In general, the reactive maintenance budget is used for immediate and urgent repairs needed to keep the highway and pavements safe for all customers. Issues reported online or picked up by our five area inspectors may be anything from a pothole to broken flag or damaged gully and can be expensive during poor weather such as flooding, frost or high winds which can cause problems for signs.
The numbers of defects are carefully monitored as is the budget at our quarterly Highway Asset Management Working Group. Problem issues can then be addressed at the meeting and preventative capital schemes used to address areas of constant pressure and repeat repairs. This may be a new drainage system where the existing infrastructure is failing or a resurfacing or reconstruction scheme where constant reactive repairs are failing.
Table 2.1 Annual repair costs
Repair | 2018 to 2019 | 2019 to 2020 | 2020 to 2021 | 2021 to 2022 | 2022 to 2023 | 2023 to 2024 |
---|---|---|---|---|---|---|
Footway kerb | 7,269 | 5,188 | 3,891 | 3,540 | 3,526 | 4,190 |
Potholes | 4,401 | 3,120 | 2,892 | 3,109 | 2,940 | 4,176 |
All Repairs | 17,415 | 12,819 | 11,332 * | 13,007 | 13,380 | 16,359 |
Cost (£) | 1,510,994 | 1,147,985 | 1,190,385 | 1,418,426 | 1,401,402 | 1,809,016 |
Repair numbers and subsequent costs for reactive maintenance fluctuate from year to year depending on the weather. 2018 being a cold winter led to increases in pothole repairs due to the freeze thaw effect on the carriageways. Similarly, 2023 to 2024 was very wet and cold with many potholes and blocked gulleys.
Footpath repairs, broken flags and kerbs make up the highest proportion of repairs annually, making up an average of 33% of all repairs (table 2.1 above). Potholes make up on average 24% of the total number of reactive repairs with the council spending an average £343,967 on repairing potholes annually from the reactive maintenance budget since 2020.
Table 2.11 Estimate of the number of potholes filled using reactive maintenance budget
Financial year | Number repaired |
---|---|
2024 to 2025 | 3476 |
2023 to 2024 | 4176 |
2022 to 2023 | 2940 |
2021 to 2022 | 3109 |
2020 to 2021 | 2892 |
2.2 Preventative (capital) maintenance
The capital budget is used for preventative maintenance for larger planned schemes such as the resurfacing and replacement of carriageways and footpaths. It is also used for bridge and structural repairs, street lighting and flooding investigations and small schemes. The schemes are selected from the annual surveys and inspections of the network as well as requests from our residents and council members.
The council is always looking to boost preventative maintenance spending with extra capital spending (prudential borrowing) in key areas such as footpath repairs, unclassified roads and traffic signal maintenance to reduce the burden on the revenue funded reactive maintenance budget. We have an invest to save project for street lighting modernisation and replacement of ageing columns which is driving down energy costs and reducing the number of reactive repairs.
All of the council's structures are part of an ongoing inspection programme set out in section 3 of the council's Highway Maintenance Plan on the council's website.
Programmes of capital work are determined from the inspections and details of the 2025 to 26 programme are shown in section 3 of this document.
The council is actively targeting the unclassified highway network which is much larger than our classified A, B and C road network and is generally in a poorer condition (see Table 2.2).
Extra council capital funding using prudential borrowing has been used to fund a large-scale thin surfacing programme since 2020 initially with micro-ashphalt and now with Ultithin - another form of thinner surfacing ideal for unclassified roads with low traffic volumes. This is part of our plan to repair and resurface greater lengths of road using appropriate materials for the road type.
Table 2.2 Planned maintenance capital programme 2024 to 2025
Asset Group | Description | Length (km) | Cost (£) | Budget proportion (%) |
---|---|---|---|---|
1 | A road | 1.8 | 252,914 | 8.6 |
2 | B road | 1.4 | 374,128 | 12.7 |
3 | C road | 3.7 | 575,647 | 19.6 |
4 | U road | 9.4 | 1,731,608 | 59.1 |
Total | 16.3 | 2,934,297 | 100 |
Details of all the proposed carriageway and footway programmes for 2025 to 2026 are shown in section 4.
Updates on all scheme proposals are also always on the council website.
The council works closely with its partners such as Northumbrian Water and the Environment Agency to develop major flood alleviation schemes. However, there are many smaller capital funded schemes related to the highway network that are carried out using the Capital preventative maintenance budget each year. In 2024 to 2025 we commenced a programme of gully repairs where damaged drainage infrastructure required a small capital scheme, over 50 such schemes are planned over the next two years to remove the burden from the reactive maintenance budget. Programme details for 2025 to 2026 are provided in section 4.
The council's reactive maintenance spends is, as explained, often determined by the weather so a key aim is to make what is a fragile network more resilient by increasing the proportion of funding dedicated to preventative maintenance. This funding may be from central government initiatives or local prudential borrowing
Section 3 - Condition of local roads
Road condition assessments on the local classified road network in England are currently made predominantly using surface condition assessment for the national network of roads (SCANNER) laser-based technology.
The unclassified highway network is surveyed using a coarse visual or manual survey with trained inspectors. (CVI)
A number of parameters measured in these surveys are used to produce a road condition indicator which is categorised into three condition categories:
- Green - no further investigation or treatment required
- Amber - maintenance may be required soon
- Red - should be considered for maintenance
A typical example is shown on figure 1.
Surveys are carried out annually in Gateshead across the network and the results are published both by the DfT and by the council on their website. The survey data is downloaded onto the council's asset management software application and used to direct the annual highway maintenance programmes.
Figure 1 Highway condition
3.1 Situation in Gateshead
The A, B and C roads in Gateshead are in a good condition; ranked in the highest road condition quartile of local highway authorities across the country. As an authority we can keep on top of repairs on these roads using capital planned maintenance budgets and targeted interventions using the latest asset management software to model current and future life expectancy.
The condition of the unclassified network (residential and industrial estates) is poor however with a backlog of 123 km in need of repair (Table 3.1). We have targeted considerable resources using different methods and techniques in the last three years to this area, the backlog of unclassified roads requiring repair has tended to remain constant at around 20% of the unclassified network indicating the extent of the problem however the latest results show an improvement for the first time in seven years.
As our neighbouring authorities have similar backlog issues on their unclassified roads the issue has been raised with the North East Combined Authority and is flagged up in the regional Transport Asset Management Plan. We continue to target the unclassified network as shown in (Table 2.2) with almost 60 % of spend in that area but annually this is still less than 10 km of the 123 km estimated backlog.
Longer term extra capital funding has been provided by government in 2023 to 2024 and onwards to 2027 including the additional Network North funding (from the cancelled HS2 project) and Pothole funding. The regional TAMP also provides certainty of funding and it is hoped this will draw the condition indicator down and away from the existing "steady state".
Table 3.1 Percentage of road network that should be considered for maintenance in Gateshead
Road class | Length (km) | 2017 to 2018 | 2018 to 2019 | 2019 to 2020 | 2020 to 2021 | 2021 to 2022 | 2022 to 2023 | 2023 to 2024 | 2023 to 2024 |
---|---|---|---|---|---|---|---|---|---|
Principal | 78.1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 |
B and C | 141.4 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 |
Unclassified | 682.2 | 18 | 20 | 19 | 20 | 24 | 21 | 21 | 18 |
Table 3.2 Road condition categories by year
Year | % of A roads in red category | % of A roads in amber category | % of A roads in green category |
---|---|---|---|
2020 to 2021 | 1 | 10 | 89 |
2021 to 2022 | 1 | 10 | 89 |
2022 to 2023 | 1 | 10 | 89 |
2023 to 2024 | 1 | 11 | 88 |
2024 to 2025 | 1 | 11 | 88 |
Year | % of B/C roads in red category | % of B/C roads in amber category | % of B/C roads in green category |
---|---|---|---|
2020 to 2021 | 2 | 16 | 82 |
2021 to 2022 | 2 | 16 | 82 |
2022 to 2023 | 2 | 14 | 84 |
2023 to 2024 | 2 | 14 | 84 |
2024 to 2025 | 2 | 14 | 84 |
Year | % of U roads in red category |
---|---|
2020 to 2021 | 20 |
2021 to 2022 | 24 |
2022 to 2023 | 21 |
2023 to 2024 | 21 |
2024 to 2025 | 18 |
3.2 Gateshead's unclassified network
The unclassified network makes up over 75 % of the total highway network at 682 km and although very urban in nature in the east and centre of Gateshead, in the west it is very rural with country lanes and some steep inclines to the Derwent and Team river valleys.
This has led to different issues arising in certain areas although the western unclassified network has lower volumes of traffic upon it the roads are more susceptible to the freeze thaw process and are not always suitable for thin- surfacing products which would be appropriate on housing estates in the built-up areas. Our strategy has been to use thin surfacing on unclassified urban roads with low traffic volumes identified as red on the CVI surveys but also with high volumes of reactive maintenance repairs. In the rural west some repairs have had to be more extensive although we have had success with jet patching in certain areas.
The council has provided extra funding to address the backlog of works on the unclassified network with prudential borrowing over the last four years to help the situation, but we would need to invest much greater funding to begin to drive down the backlog of works accrued on the unclassified network.
Figure 3.2 Unclassified network condition Winlaton Gateshead 2024
Green = up to standard
Red = work potentially required
Section 4 - Plans and programmes 2025 to 2026
4.1 Overall strategy
Gateshead Highway Asset Management Plan (HAMP) / Highway Management
The Gateshead HAMP provides the strategic framework for the management of the highway network in Gateshead. It is updated annually and reported to the Council's Cabinet. It provides the latest performance information and details progress with the key targets that have been set. The HAMP has two other key documents which provide the detail required to direct the management of the highway they are the Highway Maintenance Plan and the Highway Asset Management Framework both of which are available on the council's website.
The council has a HAMP working group where senior officers look at quarterly performance with targets and monitor scheme progress and financial management.
Outcomes from investment in the asset are monitored closely to make sure they align with strategies.
The council understands the value of highway asset management as an effective way to manage limited resources and has been developing their highway asset management plans since 2014. On the following principles:
- Data driven based on objective information - using credible and current data such as routine condition surveys, safety inspections, customer reports,
- Objective driven - with resource allocation decisions based on clear policy goals and objectives.
- Performance based - policy objectives translated into performance measures that are used for day-to-day management and for strategic management.
- Monitoring and review - performance results are monitored and reported for their impacts
A full list of policies and targets is in section 6 of the Gateshead Highways Asset Management Plan 2018 to 2030.
HAMP Targets 2024 to 2025
Action / target | Priority | Progress 2023 to 2024 and target 2024 to 2025 | Status | |
---|---|---|---|---|
Strategic / general | ||||
1 | The development of life cycle plans for different asset types in Gateshead. | High | Life cycle plans now available for all assets | Amber |
2 | Assessment of the impacts of climate change for future maintenance regimes. Development of carbon measurement (carbon calculator for materials). Development of a decarbonisation strategy for highway infrastructure maintenance | High | Conversion of traffic signal installations to LED now high priority to provide carbon/energy savings and reliability gains. Grant received from DfT. Conversion of all street lighting lanterns to LED complete. Carbon/ energy savings being accrued. Tarmac partnership commenced with carbon reduction baseline for 2023 to 2024. New warm mix and ultra thin products now being used to replace more traditional higher carbon materials. Programme to continue in 2024 to 2025. | Amber |
3 | Review inspection and repair policy to reduce repair numbers using new risk-based code of practice. | High | New risk related highway inspection policy now achieving target to reduce repair numbers and improve repair times. New policy continues to provide benefits in safety and cost savings in 2023 to 2024. (Continue to monitor performance 2024 to 2025.) | Green |
Maintenance programmes | ||||
4 | To arrest the declining condition of the council's unclassified carriageway network (residential estate roads) to bring it in line with other Northeast authorities. | High | Extra funding continues to be targeted into this area. The decline may have been arrested; improvements may require more resources. | Amber |
5 | Deal with the increasing incidences of potholes in carriageways using new methods and techniques where appropriate. | High | External funding provided to assist in 2023 to 2024; however, numbers fluctuate being dependent on weather. | Amber |
6 | Replace obsolete traffic signals equipment with new longer lasting and more energy and carbon-efficient equipment. | High | Maintenance programme commenced guided by the Imtrac asset management system. (Ongoing seeking further funding.) | Amber |
7 | Develop evidence-based ward programme for improving footway condition based on footpath hierarchy, condition, and defect records. | High | Utilised extra funding and used new footway maintenance survey (FMS). In 2023 to 2024. To continue in 2024 to 2025 | Amber |
8 | Assess and where necessary act to remedy geotechnical problems. | High | New area at Lintzford Road A694 to be addressed. | Amber |
9 | Tackle problems relating to vehicle restraint systems. | High | Full survey conducted and repair programme commenced. | Green |
10 | Develop programme for the continuous replacement of older lighting support columns. | High | 2850 new lighting support columns have already been planted as part of the ongoing column support replacement scheme. | Amber |
11 | Structural testing of lighting columns. | High | Structural programme of replacement ongoing. | Amber |
12 | Tackle deteriorating condition of signs and road markings. | Medium | Extra funding provided and programme of works continues. | Amber |
13 | Improve the management of 30,000 highway drains/culverts using a new risk-based approach to target critical locations. | High | New computerised management system now fully operational (2023 to 2024). Analysis of first 2 year's data to develop a new drainage strategy (2025). | Amber |
14 | Carry out bridge and structural inspections programme using bridge management software. | High | Ongoing programme of general and principal inspections of all highway structures. | Amber |
Information / analysis | ||||
15 | Improve links to actual cost information for schemes. | High | Some work completed. (Ongoing) | Amber |
16 | Link footway inventory data to asset database. | Medium | Completed | Green |
17 | Identify future approach towards updating inventory information. | Medium | New asset information strategy completed. | Green |
18 | Develop new skidding resistance policy and work programme expanded to B and C roads. | High | Network analysis completed. Second year of B and C road surveys completed and remedial work underway. Policy requires an update. | Amber |
19 | Update Imtrac traffic signals asset management system to manage performance and future maintenance programmes. Fault reporting system to be centralised. | High | Inventory now updated. Allowing accurate billing, life cycle planning and fault reporting. (Complete) | Green |
4.11 Best practise delivering innovation and efficiency
Gateshead Council asset officers meet regularly with their colleagues in the North East Combined Authority area to share best practise and benchmark service provision and share ideas on innovation. Repair times and standards have been successfully improved after benchmarking and new customer focused reporting systems introduced.
During 2023 to 2024 a more targeted approach was taken to footpath repairs in Gateshead. Higher risk areas with greater footfall such as in local centres, outside hospitals, schools and residential homes were given a greater priority after initially looking at the condition surveys, local feed-back and our reactive repair records.
The programme also received extra internal funding and so far over 5000m2 of footpath at a cost of £300,000 has been repaired with this programme which commenced in 2023 to 2024 and has continued into 2024 to 2025.
The council has been gradually converting its traffic signals from tungsten halogen to LED which has brought with it great efficiencies in not only carbon savings and electricity costs but also reduced the numbers of repair visits. The council has also trialled various low carbon materials for resurfacing roads from warm lay materials as opposed to hot rolled asphalt that exhibits much higher carbon production.
Other new products such as Ultithin which is a thin surfacing material suitable for lightly used estate roads are now being extensively used. Like other thin surfacing products this is a layer added to an existing surface to extend its life without the planing out and subsequent transport costs in finance and carbon. This product appears to have the advantage in terms of life expectancy over some other products we have tested in Gateshead.
We have trialled various products to deal with potholes including jet patching and have now decided to use the pothole pro from JCB this summer.
Our overall annual carbon output from materials used in highway maintenance is monitored annually. Our future aim is to continually look at new products and ways of reducing our carbon footprint in the processes involved in highway maintenance.
Section 4.2 - Specific capital maintenance plans for 2025 to 2026
4.2 Carriageway resurfacing /reconstruction 2025 to 2026
4.21 Classified and bus routes
Location | Reason for works being undertaken | Indicative cost (£k) | Length km | Benefits |
---|---|---|---|---|
A184 Consett route/slip road | Surface/binder course failure | 67 | 337 | Extend life make safe |
A184 Felling bypass | Surface/binder course failure | 71 | 118 | Extend life make safe |
A694 Spa Well Road | Loss of skid resistance | 55 | 175 | Safety |
A1114 Riverside Way | Loss of skid resistance | 20 | 50 | Safety |
A1288 Birtley Lane | Surface/binder course failure | 39 | 70 | Extend life make safe |
C302 Lead Road, Greenside | Surface/binder course failure in carriageway | 64 | 240 | Extend life make safe |
C305 North Street, Winlaton | Surface/binder course failure in carriageway | 55 | 150 | Extend life make safe |
C307 Dunston Bank, Dunston | Surface/binder course failure in carriageway | 92 | 180 | Extend life make safe |
C308 Pennyfine Road, Sunniside | Surface/binder course failure in carriageway | 49 | 245 | Extend life make safe |
Victoria Road, Bensham | Surface/binder course failure in carriageway | 72 | 268 | Extend life make safe |
C326 Askew Road West, Redheugh | Surface/binder course failure in carriageway | 50 | 130 | Extend life make safe |
Saltwell View, Saltwell | Surface/binder course failure in carriageway | 86 | 206 | Extend life make safe |
C315 Coatsworth Road / Whitehall Road, Bensham | Surface/binder course failure in carriageway | 47 | 103 | Extend life make safe |
C313 Easedale Gardens/Springwell Road/Stanley Gardens, Wrekenton | Surface/binder course failure in carriageway | 45 | 80 | Extend life make safe |
4.22 Unclassified roads
Location | Reason for works being undertaken | Indicative cost (£k) | Length km | Benefits |
---|---|---|---|---|
Strothers Road, High Spen | Surface course failure in carriageway | 24 | 133 | Extend life make safe |
Stella Bank, Stella - Low priority | Surface course failure in carriageway | 10 | 85 | Extend life make safe |
Ancrum Way, Whickham | Surface course failure in carriageway | 13 | 65 | Extend life make safe |
Prospect Terrace, Kibblesworth | Surface course failure in carriageway | 16 | 110 | Extend life make safe |
Mourne Gardens, Lobley Hill - Low priority. Condition is reasonable | Surface course failure in carriageway | 14 | 106 | Extend life make safe |
Seventh Avenue, Team Valley | Surface/binder course failure in carriageway | 49 | 101 | Extend life make safe |
Windermere Street West, Bensham. | Surface course failure in carriageway | 33 | 155 | Extend life make safe |
King Street, Bensham | Surface course failure in carriageway | 23 | 119 | Extend life make safe |
Cross Keys Lane, Low Fell | Surface/binder course failure in carriageway | 22 | 122 | Extend life make safe |
Harewood Green, Bedale Acomb Court, Allerdene. | Surface course failure in carriageway | 30 | 140 | Extend life make safe |
North Dene, Birtley | Surface course failure in carriageway | 29 | 170 | Extend life make safe |
Taylor Gardens, Pelaw | Surface course failure in carriageway | 16 | 87 | Extend life make safe |
Ryhope Gardens, Wrekenton | Surface course failure in carriageway | 24 | 105 | Extend life make safe |
Suffolk Place | Surface course failure in carriageway | 40 | 210 | Extend life make safe |
Elder Grove | Surface course failure in carriageway | 20 | 95 | Extend life make safe |
Dorset Avenue | Surface course failure in carriageway | 10 | 100 | Extend life make safe |
Windermere Street West (rear) | Surface course failure in carriageway | 15 | 112 | Extend life make safe |
4.23 Back lanes
Location | Reason for works | Cost £k | Length (metres) | Benefit |
---|---|---|---|---|
Derwent Street, Chopwell | Surface course failure | 8 | 70 | Extend life make safe |
Litchfield Terrace, Winlaton | Surface course failure | 8 | 70 | Extend life make safe |
Eleanor Terrace / Edith Terrace, Whickham | Surface course failure | 23 | 157 | Extend life make safe |
Ravensworth Terrace, Dunston | Surface course failure | 21 | 143 | Extend life make safe |
Caris Street / Roseberry Avenue, Deckham | Surface course failure | 19 | 150 | Extend life make safe |
Beacon Rise, Sheriff Hill | Surface course failure | 10 | 60 | Extend life make safe |
Rochester Terrace / Bondene Avenue West, Felling | Surface course failure | 19 | 125 | Extend life make safe |
West Row / Penshaw View, Birtley | Surface course failure | 20 | 193 | Extend life make safe |
Chilcrosse (Bleachfield), Leam Lane | Surface course failure | 20 | 120 | Extend life make safe |
Cowpath Gardens / Croxdale Terrace, Pelaw | Surface course failure | 10 | 110 | Extend life make safe |
Deneburn / Hallgarth, Leam Lane | Surface course failure | 16 | 110 | Extend life make safe |
4.24 Surface dressing
Location | Reason for works | Cost £k | Length (metres) | Benefit |
---|---|---|---|---|
C305 Pawston Road, Barlow / High Spen | Prepatch and surface dress | 105 | 1250 | Extend life make safe |
West Lane and Knobbyends Lane, Winlaton | Prepatch and surface dress | 53 | 610 | Extend life make safe |
Coach Road, Lobley Hill / Lamesley | Prepatch and surface dress | 112 | 2080 | Extend life make safe |
C306 Fellside Road, Whickham | Prepatch and surface dress | 66 | 435 | Extend life make safe |
4.25 Ultithin programme on unclassified roads
Location | Reason for works | Cost £k | Length (metres) | Benefit |
---|---|---|---|---|
Ridgeway, Leam Lane | Surface course failure | 31 | 330 | Extend life make safe |
Byron Walk, Keats Walk, Gateshead | Surface course failure | 41 | 161 | Extend life make safe |
Derwent View, Winlaton | Surface course failure | 24 | 304 | Extend life make safe |
Park Avenue, Blaydon | Surface course failure | 8 | 71 | Extend life make safe |
Runnymede Gardens, Chopwell | Surface course failure | 49 | 383 | Extend life make safe |
Larkspur Road, Whickham | Surface course failure | 38 | 228 | Extend life make safe |
Blackthorne, Sunniside | Surface course failure | 30 | 131 | Extend life make safe |
Dunston Road, Dunston | Surface course failure | 24 | 120 | Extend life make safe |
Heathfield Road, Low Fell | Surface course failure | 32 | 240 | Extend life make safe |
Holyoake Gardens, Deckham | Surface course failure | 36 | 261 | Extend life make safe |
4.3 Footways
Area where work is planned | Type of works being undertaken | Indicative cost (£k) | Length (m) | Benefits |
---|---|---|---|---|
Mountside Gardens, Dunston Hill | Replace paving flags with asphalt | 42 | 227 | Safety and improved environment. |
Queens Court, Teams | Replace paving flags with asphalt | 46 | 215 | Safety and improved environment. |
Jackson Street phase 2, Gateshead | Replace paving flags with asphalt | 63 | 157 | Safety and improved environment. |
Grisedale / Brampton Gardens, Low Fell (east side) | Replace asphalt with stone paving and kerb works | 43 | 325 | Safety and improved environment. |
Church Road, Sheriff Hill | Replace paving flags with asphalt | 22 | 93 | Safety and improved environment. |
Coldwell Park Drive, Felling | Replace paving flags with asphalt | 35 | 154 | Safety and improved environment. |
Redemarsh, Leam Lane | Replace paving flags with asphalt | 42 | 277 | Safety and improved environment. |
Jackson Street phase 1 | Re-lay paving flags | 92 | 157 | Safety and improved environment. |
B6317 Whickham Front Street | Renew existing bitmac footway surfacing | TBC | 220 | Safety and improved environment. |
Burn Road, Blaydon | Renew existing bitmac footway surfacing | TBC | 290 | Safety and improved environment. |
Dunston Bank | Renew existing bitmac footway surfacing | TBC | 450 | Safety and improved environment. |
Chester Gardens, Crawcrook | Renew existing bitmac footway surfacing | TBC | 110 | Safety and improved environment. |
Redemarsh, Leam Lane | Replace existing flagged footway with Bitmac | TBC | 92 | Safety and improved environment. |
B6315 Woodside Lane, Greenside | Replace existing flagged footway with Bitmac | TBC | 140 | Safety and improved environment. |
4.4 Structures and bridges
Area where work is planned | Type of works being undertaken | Indicative cost (£k) | Benefits |
---|---|---|---|
Tyne Bridge | Major maintenance with Newcastle City Council | 41,400 | Major maintenance required to ensure future durability of structure. Note Gateshead contribute 40% of cost. |
Gateshead viaduct | Principal inspection and PTSI stage 1 | 330 | Duty to inspect and maintain structures. Investigation of known issues. |
Gateshead viaduct | Demolition | 18,000 | Maintenance burden reduced. |
Allows town centre regeneration | Redheugh Bridge principle inspection | TBC | Duty to inspect and maintain structures. |
Redheugh Bridge | Coping stabilisation Drainage repairs | 1,000 | Address risk of spalled coping units and piers. |
Lamesley Road | Brick parapet repair | 10 | Maintain safety features |
Riding Mill Lane public right of way | Bridge replacement | TBC | Bridge does not have parapets and is at the end of its life. Repacement options being considered. |
Lintzford Road | Stabilisation of carriageway | 150 (design) TBC (construct) | Reduces risk of landslip and loss of key transport corridor. |
Scotswood bridge | Principle inspection | TBC | Duty to inspect and maintain structures. |
Blaydon viaduct | Principle inspection | Duty to inspect and maintain structures. | |
The Gateshead Millennium Bridge | Principle inspection including mechanical and engineering | TBC | Refurbishment of some mechanical and engineering elements required to ensure continued use of opening. |
4.5 Street lighting
Area where work is planned | Type of works being undertaken | Indicative cost (£k) | Benefits |
---|---|---|---|
Borough wide | Column Replacement Program | 1.5m | Upgrading lighting infrastructure |
Borough wide | High Mast Lantern Replacement | 61 | Upgrade the lighting at major conflict areas |
Metrocentre ring road | Duct/cable replacement | 150 | Infrastructure improvement |
Team Valley | Duct/cable replacement | 100 | Infrastructure improvement |
Main Gate, Team Valley | LED lantern replacement | 25 | Upgrade the lighting at major conflict areas |
4.6 Drainage /flooding
Area where work is planned | Type of works being undertaken | Indicative cost (£k) | Benefits |
---|---|---|---|
Holburn lane | Installation of two dams and culvert | 100 | To alleviate flood risk to private land and improve existing culvert inlet making it better for future maintenance. |
Gully repairs | Repair of existing restricted gullies | Not applicable | Maintenance of existing gullies to drain existing highway. |
Watergate Park reservoir | Implementation of erosion control | 500 | To bring the reservoir to latest specification to reduce risk of life in an event. |
Ridgeway surface water and flooding alleviation scheme (SWFAS) | Installation of new manhole and gullies. | 40 | To alleviate flood risk to highway for local community. |
Durham Road SWFAS | Removal of existing drainage and installation of new highway drainage. | TBC | To alleviate flood risk to highway for local community and business. |
Arran Road SWFAS | Installation of new gully into footway to alleviate flood risk | 20 | To alleviate flood risk to highway for local community. |
Community Alert System (CAS) | Installation of bollards | 10 | To inform customers within the community of flood risk that will provide time for customers to prepare. |
To summarise we plan to:
- resurface over 55 streets
- improve more than 20 footways
- repair and inspect 11 structures
- replace hundreds of lighting columns
- carry out 10 flood relief schemes
In an average year we repair 3318 potholes.
Section 5 - Streetworks
Gateshead Streetworks permit scheme was established in 2020. It has grown from a team of one Streetworks Controller, two Permit Support Officers and one Inspector to three Permit Inspectors and three Permit Support Officers under the supervision of the Streetworks Controller.
The team assess permits to manage and minimise delays and other impacts on all road users, promote best practice and enhance coordination, collaboration, and cross boundary cooperation across the North East region, particularly in the area covered by the North East Combined Authority. The team actively drive compliance with inspections and issue penalties and fines, in accordance with the legislation, when noncompliance is identified.
It's important that new resurfacing works are not undermined by being repeatedly dug up by utility companies and we use our Streetworks permit powers to manage this.
Key to this is coordination and good working relationships between the council and utility companies with the council being seen to be acting fairly to all parties and having regular coordination meetings.
Operationally we monitor the permit durations and challenge any that seem excessively long as well as seeking to optimise resource allocation from the utility side. We carry out regular street works inspections to make sure if a road has to be dug up it is properly reinstated to appropriate standards with any issues addressed promptly.
We also focus on any defects that may be apparent when the reinstatement has been finished and also at regular prescribed intervals after the reinstatement has been completed.
Section 6 - Climate change and resilience
6.1 Decarbonising maintenance operations
The council has established a carbon reduction group in partnership with Tarmac which has the council's current term maintenance contract. We have begun using warm lay road resurfacing materials (instead of high carbon, hot lay materials) and a new thinner surfacing product with a much-improved finish and greater longevity both of which have much lower (carbon footprint).
The annual carbon reduction from the use of warm lay materials for resurfacing and ultrathin materials equates to some 64 tons of CO2e (the standard measurement of greenhouse gas) in the 2023 to 2024 programme. The aim going forward will be to find greater annual savings to improve on this baseline and to use this information to assist the decision-making process when it comes to choice of materials, treatments and intervention timing. This work will allow us to develop a new highway decarbonisation policy/strategy in 2025 for highway infrastructure to add to the work already providing carbon reduction benefits with street lighting and traffic signals.
Recent improvements in management of our traffic signals with a new asset management system and inventory is allowing us to target sites for repair on obsolescence and reliability. The conversion of all 180 traffic signal sites from the existing tungsten halogen lighting to LED is now very much a priority with some 50 sites outstanding.
The conversion is expensive, however the benefits in energy and carbon savings as well as reliability are excellent. In 2023 to 2024 a successful bid to central government has provided a grant of over £100,000 to be used on upgrading old equipment. The successful LED conversion programme with our street lighting estate has also provided energy and carbon savings and was a key target in earlier years of the HAMP.
6.2 Network resilience
A key aim of the Gateshead HAMP is to improve the resilience of the highway network to deal with severe weather events particularly flooding. For the last 2 years we have been using a gulley management software programme to look at the performance of all our 30,000 highway drains. The information is used to identify areas requiring greater attention at sites with known flood risk issues. This information will allow us to develop a strategy to make the network more resilient with resources directed to the areas of greatest need. The same data is collected on culverts and other blockage points to ascertain which screens and entrances need to be cleaned more regularly and in advance of bad weather forecasts.
Resilience in terms of choosing the correct surfacing materials to last in different areas of Gateshead has already been discussed in section 3.2 similarly carefully monitoring faults and frequent issues relating to traffic signals and street lighting and changing to longer lasting equipment also builds in resilience into the network.