Date: 3 July 2026
Dear resident
We have been advised by the Contractor BAM of the following upcoming works:
- Friday 3 July 2026 (evening) - deliver and place stone to the ground adjacent to the east boundary wall for the foundation for the scaffold protection screen. This can only be done in the evening due to the required A167 lane closure which is not permitted during the day.
- Monday 6 July 2026 to Wed 8 July 2026 (daytime and night time) - install concrete blocks for scaffold counterweight.
- Wednesday 8 July 2026 for approximately 2 weeks (daytime) - install scaffold protection screen
BAM envisage that these works should not be too disruptive and the use of loud noise producing equipment will not be required.
All our news updates on the flyover demolition project can be found at Gateshead Highway (A167) flyover.
Translation services
To translate this letter into another language, please click 'Listen and Translate' (top right of page), and use the translation icon to choose the language you need.
Find out more about our listen and translate tool Recite Me.
If you need more help, ask your housing officer and this can be arranged.
Yours faithfully
Sharon Davidson
Housing Asset Management