Regulatory judgement improvement plan
5. Backlog of repairs
Regulatory standard | Safety and Quality |
Area of weakness | High volume of repairs works orders passed their target |
Intended outcome(s) | Reduction in outstanding repairs. Increase in satisfaction with repairs and time taken to complete the most recent repair. |
Lead | Ian McLackland (Service Director, Repairs and building maintenance). Laura Atkinson (Service Manager, Repairs and voids). |
Target completion | Less than 825 by December 2025 (15% of works in progress (WIP) target). By the end of 2025 to 2026:
|
Step targets (where possible) | Total WIP month end targets: June - 1547 July- 1407 August- 1267 September- 1092 October- 952 November- 812 |
Short/medium/long term plans | Reduction in outstanding repairs.Short TermTo reduce to less than 25% of WIP. Medium TermTo achieve 15% of WIP target by December 2025. Long Term:To maintain at no more than 15% of WIP target. Satisfaction with overall repairs serviceShort term:72% (median quartile) Medium term:79% (upper quartile) Long term:Maintain upper quartile performance levels. Satisfaction with time taken to complete the most recent repairShort term:67% (median quartile) Medium term:75% (upper quartile) Long term:Maintain upper quartile performance levels. (As per RSH 2023 to 2024 results for the above quartiles) |
Organisational risks |
|
Potential impact on customers if we do not achieve intended outcome |
|
Current position | Works orders have continued to progressively decrease, reaching 841 at the end of November 2025. Although slightly above the step target of 812, this represented less than 15% of works in progress (WIP) and met our medium‑term plan. Works orders did rise to 933 at the end of December against a step target of 878, equating to 15.93% of WIP. This temporary increase was mainly due to the Christmas shutdown and reduced trade availability. We expect performance to return within the 15% target by February and to remain on track with the long‑term plan thereafter. A project has been carried out to understand the barriers to no access from an organisational and customer perspective. An action plan is currently being developed to address the recommendations from this exercise. TSM results 2024/25 At end of quarter 3 2025/26, |
RAG | Amber - Partially on target |
Evidence | Reports to Strategic Housing Board, Housing Environment and Healthy Communities Overview and Scrutiny Committee (HEHC OSC), Housing Portfolio and Corporate Management Team. Key Performance Indicators Performance reports to HEHC OSC and Strategic Housing Board. Repairs Performance - Presentation to HEHC OSC 17 November 2025 |
Last updated: January 2026